Confirmed by record

MISO Project 51141 documents a 1,500 MW Hobart load addition and related 345-kV transmission work.

Confirmed as a transmission planning record, not current delivered service.

What the reviewed record shows

MISO’s February 2026 planning record identifies a new Hobart 345-kV load addition, related transmission work and a March 2027 expected in-service date. The record documents the planned grid pathway; it does not mean the full data-center load is already connected or operating.