ConfirmedAmazon’s application shows 782 diesel generators.
Confirmed, with important operating context.
The submitted application lists 766 critical emergency generators and 16 support emergency generators. It describes them as backup equipment for interruptions in electrical service, not as the planned everyday power supply.
ConfirmedThe generators total 2,119 MW.
Confirmed as combined backup nameplate capacity.
The application states approximately 464 MW at SBN520 and 1,655 MW at SBN750. Nameplate backup capacity is not the same thing as expected simultaneous routine generation.
ConfirmedThe site would hold about 5.5 million gallons of diesel.
Confirmed as rounded storage capacity.
Adding the listed belly tanks and 26 bulk tanks produces 5,466,277 gallons of storage capacity. Storage capacity does not establish annual fuel consumption.
ConfirmedThe proposal includes 26 data-center buildings.
Confirmed.
The application proposes six buildings at SBN520 and twenty at SBN750.
MisleadingThe Hobart proposal has up to 25 buildings and possibly 24 diesel generators per building.
Those estimates are now outdated.
The opposition website’s published estimate predates Amazon’s July 2026 air application. The submitted application identifies 26 buildings and an exact proposed inventory of 782 generators: 766 critical units and 16 support units.
MisleadingThe diesel generators will create continuous engine noise and exhaust.
Operation can be consequential, but “continuous” is not supported.
Amazon’s application describes the diesel fleet as emergency backup. Generator noise and exhaust occur when engines run for emergencies, testing, maintenance or other allowed operation. Cooling and other mechanical equipment may operate routinely, but that is not evidence that the diesel engines will run continuously.
MisleadingSynthetic minor means the source is minor only on paper.
The phrase is real; the conclusion omits how the category works.
The application says uncontrolled potential emissions would exceed major-source thresholds. It requests controls and emission limits intended to keep limited potential emissions below applicable thresholds. If IDEM issues those conditions in a federally enforceable permit, they become legal operating limits—not voluntary paper promises. They remain proposed until IDEM acts.
MisleadingHobart is currently going through the Title V permit timeline.
The submitted Hobart application requests a FESOP, not Title V.
Amazon requests a New Source Minor PSD/Emission Offset construction approval and a Federally Enforceable State Operating Permit. IDEM’s current table lists public notice for a New Source FESOP Minor PSD/Emission Offset review but does not list proposal to U.S. EPA. EPA’s separate objection and citizen-petition process applies to certain Part 70/Title V permits.
UnsupportedThe submitted Hobart design establishes a 97% particulate-emissions reduction.
The 97% figure is not supported by Amazon’s Hobart application.
For its potential-to-emit calculations, Amazon uses 68.6% as the conservative filterable-PM control efficiency. The application lists manufacturer options ranging from 68.6% to 75.6% for filterable PM and says the final control-system selection had not been made.
ConfirmedUncontrolled emissions would exceed major-source thresholds.
Confirmed as a potential-to-emit calculation.
The application expressly says uncontrolled potential emissions of NOx, CO and VOC appear greater than major-source thresholds. Potential-to-emit is a regulatory worst-case calculation, not a forecast of expected annual emissions.
UnsupportedIf the grid is delayed, Hobart will become the next Lebanon and Amazon will run the diesel fleet as bridge power.
Not supported by the current Hobart record.
Lebanon involved an explicit, separate temporary natural-gas generation proposal. The Hobart records reviewed show emergency diesel backup, an approved NIPSCO service contract, GenCo generation resources and a MISO transmission project. No reviewed Hobart filing establishes a plan to use the 782 diesel generators as Lebanon-style bridge power.
MisleadingNothing limits how often the generators can run.
Federal rules distinguish emergency and non-emergency operation.
The federal emergency-engine rule has no hourly ceiling during a genuine emergency. It generally allows up to 100 hours per engine for maintenance and testing, with a restricted 50-hour non-emergency subset counted inside that 100. The application also proposes combined emission caps and hour-meter records. Ordinary bridge generation does not automatically become emergency operation.
MisleadingNo environmental review has been performed for the project.
A limited stormwater technical review exists; a unified review is different.
The October 21, 2025 construction-stormwater technical review found the mass-grading plan adequate for the minimum City stormwater and IDEM construction-stormwater requirements and required a Notice of Intent. The review expressly says it does not cover every other local, state or federal permit. It is therefore evidence of review—not proof that every environmental question has been resolved.
UnsupportedThe linked data-center noise study predicts what Hobart homes will hear.
It is not a Hobart-specific acoustical study.
The linked 2022 report models sites in Northern Virginia. Its author describes it as a basic predictive analysis and says the results are not exact. It can identify questions worth testing, but it does not use the Hobart campus layout, equipment plan, barriers, terrain or receivers and cannot establish Hobart neighborhood sound levels.
Missing contextThe project receives 35-plus years of tax abatements.
The duration is real, but the shorthand blurs distinct incentives and payments.
The approved agreements provide a 10-year, 100% real-property abatement for each eligible building and a separate 35-year, 100% exemption for qualified enterprise IT equipment in each eligible building. The community agreement also schedules $175 million in contributions and separate per-building impact payments. Some scheduled contributions may be reduced by annual impact payments, and the schedule alone does not prove every payment has already been received.
Missing contextThe promised 400 jobs are not legally enforceable.
They are estimates, not an unconditional hiring guarantee, but accountability exists.
The project-wide Statement of Benefits estimates more than 400 permanent Amazon positions at $37.44 per hour, plus contractor positions. The agreement says the City cannot compel the investment or jobs. It also requires annual compliance reporting, allows job and wage information requests, and permits abatement denial for a demonstrated material failure to substantially comply, subject to reasonable-nearness, force-majeure, cure and appeal provisions.
OpinionThe data center is heavy industrial development that does not belong near homes.
That is a land-use judgment, not a self-proving factual conclusion.
The scale is industrial in ordinary language, but Hobart’s zoning ordinance addresses data centers in the M-1 Light Manufacturing district. Whether this use belongs at the location is a policy opinion residents and officials may debate; it is not established merely by labeling the project “heavy industrial.”
MisleadingA judge ruled that Hobart illegally approved the data-center project.
No. The reviewed orders do not declare the project illegal; the only final merits ruling identified confirmed the City’s ERA and real-property tax-abatement actions.
On February 18, the court denied the residents’ tax/ERA petition and confirmed the Common Council’s ERA designation and real-property abatements. On March 26, a different court dismissed or barred the first-fill-permit challenge because the plaintiffs had not exhausted the City appeal process and had not timely filed the administrative record; it expressly did not reach the requested preliminary injunction. Reconsideration was denied April 13. Later fill-permit and site-plan claims remain pending, so the record is favorable to the City on the issues already decided but is not a blanket ruling on every project approval.
MisleadingThe residents’ lawsuits have been fully dismissed.
No. One petition ended in a final trial-court ruling favorable to the City, while two related judicial-review matters remain active.
The February 18 order denied the tax/ERA petition and confirmed the ERA designation and real-property abatements. The March 26 order disposed of the first-fill-permit challenge on procedural grounds, and the April 13 order denied reconsideration. But the original case continued with amended claims and dispositive-motion briefing, and a third case filed June 8 challenges the May 7 site-plan approvals. A joint consolidation motion was filed; no order granting consolidation was identified in the records reviewed through July 26, 2026.
MisleadingIf Amazon exits early, existing NIPSCO customers automatically inherit the project costs.
The approved contract contains specific exit and customer protections.
Cause 46322 describes a 15-year customer contract, an ultimate-parent guaranty, pre-operation and early-termination payments, and required IURC notice if specified termination events occur. The default allocation places project-related electric and transmission upgrade costs on Amazon or GenCo. Those protections materially reduce cost-shift risk, but they are not a promise that every imaginable future cost can never be proposed; a later allocation would require a docketed proceeding and a customer-benefit showing.
UnsupportedCurrent NIPSCO electric rate increases were caused by the Hobart Amazon project.
The current approved record does not support that attribution.
NIPSCO’s current multi-step base-rate increase was approved in Cause 46120 in June 2025, with the final step tied to 2025 plant balances. The IURC’s 2026 affordability presentation identifies the principal drivers as previously approved solar, storage and delivery-system investments. The Hobart Amazon contract and GenCo resources were approved later, in June 2026, under separate orders that assign project-related costs to Amazon or GenCo. A customer’s bill can also change because of usage, fuel factors and other riders, so a bill increase alone does not identify its cause.
Missing contextAttorney-fee invoices prove Hobart taxpayers ultimately paid all data-center professional and litigation costs.
High-confidence probability: qualifying project-review costs are developer-reimbursable, but final payment proof is pending.
Hobart Municipal Code Chapter 155 requires a developer seeking covered land-use or financing actions to execute a project-specific reimbursement agreement and deposit funds for actual attorney, engineering, technical, financial, advertising and recording costs. The 2026 fee schedule repeats that framework, and City minutes show reimbursement agreements being used on other developments. That creates a high-confidence probability that qualifying data-center review costs were covered by reimbursement arrangements. It does not, by itself, prove that every reported invoice, the cited $205,000 total or the City’s defense of the resident lawsuits was reimbursed. The Amazon-specific agreement, deposit records and payment ledger are still needed.
Missing contextA reported $205,000 in City legal spending produced a guaranteed return of more than $1 billion.
The billion-dollar figure is a long-term revenue projection—not a realized or guaranteed net return.
Mayor Huddlestun has described projected payments of $102 million in 2026, $43 million in 2027, $40 million in 2028 and about $50 million per year after full buildout. He separately projected approximately $1.5 billion in additional revenue over 35 years. The approved community agreement supports a $175 million contribution schedule and separate per-building impact payments, but future totals depend on construction, occupancy, assessments and contract conditions. The reviewed public record also does not independently establish the cited $205,000 legal-cost total.
MisleadingThe March 2026 webinar proves each Hobart generator is limited to about 10 operating hours per year.
The webinar described an expected average—not a legal maximum.
Amazon presenters said backup generators operate about 10 hours per year on average, mostly for testing. That statement may describe Amazon’s operating experience or expectation, but it does not replace the federal runtime categories. Genuine emergency use has no federal hourly ceiling; maintenance and testing generally fall within a 100-hour allowance, including a restricted 50-hour non-emergency subset.
Proposed / pendingThe completed Hobart campus is expected to use about 14 million gallons of water per year.
This is an Amazon projection presented in the webinar.
Amazon said the campus is expected to average 14 million gallons annually and use outside-air cooling about 98% of the year. The webinar did not provide the underlying hydraulic model or an independently reviewed operating record, so the figures should remain labeled as company projections until supporting records are published.
Proposed / pendingThe webinar proves nearby homes will experience sound only in the low-50-decibel range.
The low-50s figure is a modeled design target, not a measured result.
Amazon’s acoustical consultant said the site was designed for low-50-decibel sound at the property line under conservative summer assumptions. Hobart’s adopted ordinance establishes a 65-decibel property-line maximum, but the webinar did not publish the complete Hobart acoustical model, receiver assumptions or post-construction measurements.
UnsupportedThe webinar identified an independent Hobart environmental or health-impact study.
No specific independent Hobart health study was identified.
During the Q&A, the moderator asked about independent environmental and health studies. The response described Amazon’s assessments, permitting, monitoring and agency oversight, but it did not name a completed independent Hobart health-impact study. That does not prove harm; it identifies an evidence gap.