Browse source titles, dates, status, descriptions, and the public findings they support. Research Pass opens available full records or their registered original websites, with search and Evidence Navigation over approved indexed records. Pending intake is labeled on its source card. Opening records uses no credits.
The $7.99 one-time Research Pass includes 20 Research Brief credits. One citation-verified completed brief uses one credit; failed, unsupported, canceled, or rejected work uses none. Refill packs require an existing pass. Northshore Gen charges for the work of locating, checking, classifying, maintaining, organizing and presenting the correct sources, plus direct access through the curated library. The underlying records remain the property of their government, company or publisher issuers.
final
IURC Final Order, Cause No. 46322
Publisher / issuer: Indiana Utility Regulatory CommissionClassification: Final government regulatory orderPublished / issued: June 17, 2026
Controlling primary source for what the Commission approved: the NIPSCO-Amazon customer contract and related GenCo power-purchase arrangements, with service expected to begin in 2027 and ramp through 2032. At Amazon’s projected full load ramp, the order estimates residential bill credits of about $7 per month, or $82 per year.
Used to verify: Power plan, Service schedule, Customer protections, Projected residential bill credits
The site is ready for IDEM’s draft and final documents
submitted
Amazon-submitted air-permit application
Received by IDEM July 24, 2026
IDEM application 089-50590-00739 is listed in Draft processing status as of October 1, 2026. No draft permit has been published for public comment. The application is not an IDEM-issued permit.